The first batch of 150 machines of Antminers S19 has already been delivered to the facility and soon the mining equipment will be installed on the shelves. Currently, on the site there are modular data centers designed to accommodate modern S19 devices.
Additionally, a special canopy is constructed for the cold corridor, in which warm air is mixed to prevent snow from falling, as well as to protect the equipment from excessive cooling and the most severe blizzard. In the future, we will use another workshop that is under commissioning.
To date, the first stage of capacity has been opened – 11.2 MW. Next year, it is planned to increase the capacity to 31mw.